Energy market
Connection agreements considered a reportable fundamental data item under the REMIT Regulation
Saturday, 20 October 2012 17:59

 

Classifying connection agreements as REMIT fundamental data item is not obvious and does not follow literally from the regulatory language. However, if such classification is correct, the electricity generators should immediately include such data in their REMIT reports.

 

Read more...
 
What can be expected in 2013 as regards legislative developments in the energy market
Thursday, 16 August 2012 06:13

 

2014 has been politically set as a target for the completion of the European internal market for electricity and gas. It is useful to know the schedule for adopting the main network codes in that regard.

 

Read more...
 
Reporting for non-standardised wholesale energy market contracts under REMIT framework pursuant to ACER guidelines
Wednesday, 08 August 2012 06:52

 

Reporting for non-standardised wholesale energy market contracts under REMIT Regulation will not be an easy task for market participants.

 

Given the non-standardised contracts are to be reported to ACER directly by market participants (and not by trading venues), the former are allowed more time for contract verification against reporting schedule. The one-month period seems to be sufficient for such an assessment even when it comes to complex and complicated contracts. Moreover, mandatory submitting to the ACER the pdf file of the entire contract enables additional examination of the contract by ACER services.

 

Read more...
 
European Single Electricity Balancing Market - state of play
Monday, 25 June 2012 06:57

 

Assuming Framework Guidelines become binding law, and the fact intermittent generation as the PV or wind sources have very low variable costs, it is probable in the future Single Electricity Market baseload fossil-fueled generation like coal and gas will gradually be squeezed out from providing balancing services.

Investment outlays engaged in these sources will probably be recovered over longer periods due to contained periods of operation of these units on the electricity balancing market. In such a situation it appears more and more questionable, whether the investors decide to engage in new sources of fossil-fuel generation.

ENTSO-E however engages in a dispute with the European energy regulator ACER over the content of the Framework Guidelines.

 

Last Updated on Sunday, 05 August 2012 13:33
Read more...
 
Registration for REMIT – requirement to reveal corporate structures
Saturday, 28 April 2012 16:52

 

As market participants will not be allowed to trade until they are registered, it may potentially represent a barrier to trade in the internal energy market.

Registration will not be a one-off event, but rather an ongoing requirement due to obligation to keep information provided up-to-date. From the practical point of view it is therefore necessary to establish within corporate structures of market participants arrangements ensuring that new requirements will be properly and timely discharged.

It should be noted that market participants are under obligation to register even if they are located outside the European Union.

 

Another issue of potential significance for the wider market is the commercial exploitation for data contained in the part of the register publicly revealed by ACER.

 

Read more...
 
100 MW outages as REMIT inside information
Tuesday, 24 April 2012 16:44

 

Somebody my ask why exactly 100 MW (and above) outage is treated as inside information under REMIT Regulation and what is the legal basis for such determination...

 

Read more...
 
Power exchanges – uniform EU regulation desirable
Saturday, 21 April 2012 14:13

 

1. Are there in any Member State any energy exchanges which do not qualify as regulated markets or MTF as defined by MiFID (for instance act under specific national legislation divergent from financial markets regulations)?

2. Do the energy exchanges referred to under point 1 trade in physically settled commodity (electricity) forwards?

3. Are transactions mentioned in points 1 and 2 captured by MiFID?

 

Read more...
 
Contentious collateral in EMIR draft technical standards
Monday, 16 April 2012 06:15

 

It seems that there is no agreement between European Supervisory Authorities and non-financial market participants as regards draft Technical Standards on risk mitigation techniques for OTC derivatives not cleared by a CCP under the Regulation on OTC derivatives, CCPs and Trade Repositories (the draft RTS).

 

Read more...
 
Rumours in the practical application for REMIT – interlinkages with the emissions market
Wednesday, 11 April 2012 06:39

 

There are grounds for applying certain regulatory guidance elaborated under financial instruments’ market abuse regime to wholesale energy products regulated by the REMIT Regulation. The best practice for the treatment of rumours seems to be good example.

 

These points might also be of relevance for emitters of greenhouse gases, considering interdependencies between electricity and carbon price curves and the future potential covering of emissions allowances by the financial instruments legislation.

 

Read more...
 
Transitional provisions and derogations in the ENTSO-E Draft Network Code for Grid Connections of Generators – issues that must not be overlooked
Thursday, 22 March 2012 19:08

 

An existing generating unit which is not compliant with a provision of the Network Code should apply for derogation within 12 months from the day the requirement, of which it is not compliant with, becomes applicable.

 

The network operator will have the right to refuse the operation of the generating unit, if the 12 months period terminates without an application for derogation.

 

Read more...
 
What precisely electricity generators should publish as inside information under REMIT Regulation
Monday, 23 January 2012 06:25

What precisely should be published under new disclosure scheme for wholesale energy products?

ACER Agency in its Guidelines built its list consisting of three main items:
- any planned outage, limitation, expansion or dismantling of capacity of one generation unit that equals or exceeds 100 MW, including changes of such plans,
- any unplanned outage or failure of capacity that equals or exceeds 100 MW for one generation unit, consumption or transmission facility, including updates on such outages or failures,
- any other information that is likely to have a significant effect on the prices of one or more wholesale electricity product if made public;

the last one however is quite spacious.

But ERGEG’s catalogue released in December 2010 as regards electricity generators stipulated the positions for disclosure far more extensively and specifically.

Read more...
 
How to publish inside information under REMIT Regulation
Wednesday, 11 January 2012 08:31

Is the publication on market participant’s own website the sufficient discharge of the disclosure obligation on wholesale energy market?

Read more...
 
ACER publishes guidelines on REMIT Regulation but certain issues still require urgent reaction of the Agency
Tuesday, 27 December 2011 22:57

 

The main body of the REMIT Regulation applies from 28 December 2011. So, practically, it is useful to precisely define what arrangements energy firms should have in place as of that date.

The newly published ACER guidelines on REMIT coincide with the release of the ‘CEER final advice on the regulatory oversight of energy exchanges, A CEER Conclusions Paper’. Perceived jointly, the considerations of the Union and the national energy regulators, lean towards the  reflection what we find at the end of the regulatory direction started by REMIT. The problem particularly concerns vertically integrated undertakings.

 

Read more...
 
Europe-wide passport for wholesale trading in electricity and gas, MiFID passport or REMiT registration – a field for analysis for energy traders
Saturday, 17 December 2011 20:43

 

The thorough re-calibration of energy trading licensing regime is looming. Besides standard registration required by the REMIT Regulation, the wholesale energy market participants will have the option for choosing either Europe-wide passport for wholesale trading in electricity and gas or MiFID passport – depending on the projected extent of business activity.

 

Market participants remaining beyond the scope of MiFID, will have to, however, regularly and on an ongoing basis, monitor exemptions foreseen by this Directive (currently undergoing the revision under the so-called MiFID II and MiFIR procedures) and the character of contracts concluded on the market so that not to run the risk of a charges of providing financial services without proper authorisation.

 

Read more...
 
<< Start < Prev 1 2 3 4 5 Next > End >>

Page 4 of 5

Search

Copyright © 2009 - 2017 Michal Glowacki. All rights reserved.
The materials contained on this website are for general information purposes only and are subject to the disclaimer