Energisation Operational Notification (EON)
European Union Electricity Market Glossary


 

 

Energisation Operational Notification (EON) is a notification issued by the relevant system operator to a power generating facility owner, demand facility owner, distribution system operator or HVDC system owner prior to energisation of its internal network (Article 2(63) of the Network Code on Requirements for Grid Connection of Generators (NC RfG)).

 

An EON entitles to energise the internal network by using the grid connection.

 

 

 

Article 34 of the Network Code on Requirements for Grid Connection of Generators

Energisation operational notification for type D power generating modules

 

1. An EON shall entitle the power generating facility owner to energise its internal network and auxiliaries for the power generating modules by using the grid connection that is specified for the connection point.

 

2. An EON shall be issued by the relevant system operator, subject to completion of preparations including agreement on the protection and control settings relevant to the connection point between the relevant system operator and the power generating facility owner.

 

 

 

An EON is also present in the provisions of the Network Code on Demand Connection (see box).

 

 

 

Article 23 of the Network Code on Demand Connection

Energisation operational notification


1. EON shall entitle the transmission-connected demand facility owner or transmission-connected distribution system operator to energise its internal network and auxiliaries by using the grid connection that is specified for the connection point.


2. An EON shall be issued by the relevant TSO, subject to completion of preparations including agreement on the protection and control settings relevant to the connection point between the relevant TSO and the transmission-connected demand facility owner or transmission-connected distribution system operator.

 

 

 

Further details concerning the EON procedure are to be specified and made publicly available by the relevant Transmission System Operator (TSO) - Article 22(3) of the DCC.

 

 

Links

 

 

Interim Operational Notification (ION)

 

Final Operational Notification (FON)

 

Limited Operational Notification (LON)

 

Power-generating module document (PGMD)

 

 

Last Updated on Wednesday, 30 November 2016 21:35
 